One of the most important purposes of development of computer systems was the database application which could have been used on them. Data processing drove growth of computer processor speed. In fact, data processing predates the computers; punched cards were used in the US for collecting data for census during beginning of 20th century. Earliest […]

11246 ERP Service Module – Planning, Warranties and Contracts

Service Planning – Attending of unscheduled maintenance tasks arising out of breakdown and faults both for internal and external customer is an important service activity of any organization. However, bulk of service activities arise out of planned service activities. For internal customers, this may be routine maintenance of plant and equipments, arising out of preventive […]

12781 Step 1: Collect and Review Primary Information

The project begins when the top management assigns responsibility to the Project Champion. The Project Champion usually delegates the task of preparing the Project Charter to another team member. It is important for both the Project Champion as well as the team member to understand what information is required. Here are tips on how to […]

12963 Creating a SIPOC Chart

The SIPOC Chart, being one of the fundamental documents of any process improvement project must be developed in such a manner that it is easy to understand. It must also be coherent with the logic inbuilt in the process. There is a method which has been described to ensure the proper development of the SIPOC […]

10889 Why Radical Disruption is not Always Beneficial: Lessons from Demonetization

Is Demonetization an Example of Radical Disruption? The Indian Economy and Body Polity was treated to a Shock Exercise when the Indian Prime Minister, Narendra Modi, decided to demonetize 80% of the total currency in circulation at a stroke of a sudden announcement and in a most unilateral and arbitrary manner. This policy announcement that […]

Search with tags

  • No tags available.

Introduction

This article is a follow up of the earlier one related to the project management processes for an automation tool. This tool is to be used for automating the processes of a maintenance project in a software company.

Rework

A rework can arise due to:

  • Change in scope
  • Quality of the deliverables not up to the mark
  • Change in requirements that is essentially a change in scope

Change in Scope

Rework arising due to change in scope means that the project baseline has to be modified and corresponding changes made to the project management plan, resource plan, schedule plan etc.

Any change in scope affects not only the schedule but the cost as well. So, a proper scope change mechanism would take into account the effect to the schedule as well as the costs associated in carrying out the same.

Considering the scenario where 20 percent of the rework has to be done in the context of the automation tool it means that:

  • New features have to be added to the tool

  • And new requirements have to be taken into account

There are two aspects of scope management. One is preventive in nature and the other is corrective actions. Rework due to the new requirements falls into the corrective category and a formal change request has to be raised that takes into account the various parameters like changes to the cost and the time.

Rework due to Quality

This is also known as defective repair. In the context of the automation tool, it would mean that the deliverables have not been found satisfactory during testing. The rework has to be fit into the existing schedule as the project charter specifies timely delivery and hence any change to the schedule would involve changes to the cost of the project.

Integrated Change Control

Any change requests should go in through an integrated change management system. All the corrective, preventive and defect repairs are covered here. Any change to the project management plan is covered here.

The following steps have to be taken to accommodate the 20 percent change in the scope

  • All the stakeholders have to be informed about how the change would affect the cost, time, risk and other project objectives including quality

  • All the change requests have to be categorized as corrective or preventive and suitable action recommended

  • Some of the changes can be rejected if found not feasible from a technical or a functional standpoint

  • The proposed changes have to fit within the reason the project was initiated. This means that the overall project objectives and the purpose cannot be lost because of some rework.

  • Do a root cause analysis and find out whether any further changes can be avoided

  • The project management plan has to be updated

  • The change control board has to be constituted and made functional

  • All the changes to the deliverables have to be reviewed

  • The configuration management should be followed in terms of using the correct versions of the components of the project management plan and are being updated in a controlled fashion

  • Update the project baselines

  • Update the project management plan

In addition, the project manager has to make sure that:

  • The final requirements are obtained as soon as possible

  • The risks are identified upfront

  • Institute a process to control changes

  • Roles and responsibilities of the team members are defined

  • The business case has to be re-evaluated if the changes are excessive

  • Allow only change control requests that are approved by the change control board

  • If the changes are excessive and would deviate from the overall project objectives, terminate the existing project and start a new one

Conclusion

The one overriding priority is to ensure that the customer’s requests are met without compromising on the internal stakeholders needs. A fine balance has to be struck between the objectives of the internal and the external stakeholders.

Article Written by

MSG Team

An insightful writer passionate about sharing expertise, trends, and tips, dedicated to inspiring and informing readers through engaging and thoughtful content.

Leave a reply

Your email address will not be published. Required fields are marked *

Related Articles

Costs in Project Management – Costs associated with the Projects

MSG Team

Communications Management during Project Planning

MSG Team

Bidding as an Essential Skill for Project Managers

MSG Team